Change a task link

StakePoint Team -

When you link two tasks, StakePoint creates a finish-to-start dependency between them by default — the second task can’t start until the first task finishes. But that’s not your only option. StakePoint supports four types of task dependencies, which cover the predecessor-successor relationships of most projects. Here’s how to change a link type:

  1. Select> Gantt.

  2. Double-click the link line between the two tasks.


  1. Pick a dependency type from the Type list.    

  2. To get rid of the link entirely, pick (None) from the Type list.

 

 